Regulators to review OGE

Oklahoma regulators will meet this week and take up the consideration of the 2026 energy plans of Oklahoma Gas and Electric Company.

The agenda for the Thursday afternoon meeting (1:30 p.m.) shows Corporation Commissioners will hold a: Presentation and discussion, including public comment, regarding the Draft 2026 Integrated Resource Plan of Oklahoma Gas and Electric Company.

The plan is only a draft but in it, OG&E laid out its proposals to meet the energy demands for the year, including its suggested expansion of power-producing projects. The plan is also an effort by OG&E in defense of its requests to be considered by corporation commissioners.

“OG&E’s 2026 IRP forecasts a need for incremental generation capacity primarily due to continued expansion of the SPP Resource Adequacy framework and continued strength
in regional demand trends,” stated the Executive Summary in the plan and referred to the needs of the Southwest Power Pool, the electric grid of which Oklahoma is a member.

“OG&E’s 2024 and 2025 IRPs clearly identified additional capacity needed to support OG&E’s service area as load growth has accelerated and market dynamics continue to shift. In 2024, OG&E issued multiple RFPs for new and existing generation resources, has since received regulatory approval for several projects arising from these RFP efforts, and is currently seeking regulatory approval for an additional project that resulted from
these RF”

The company further explained it is seeing load growth from a mix of industries which requires a more adaptive and scalable approach to long-term resource planning.

“Changing SPP rules for accreditation, forecasting, outages, and Planning Reserve Margin (PRM) levels are creating a highly volatile and dynamic capacity environment that must be evaluated each season. At the same time, federal policy shifts, environmental regulations, and supply chain pressures add operational uncertainty that introduces volatility into OG&E’s
resource planning.”

 

AGENDA
Item Topic

I. A. Call to order
B. Announcement concerning public notice
C. Determination of quorum

II. Approval of minutes of prior meeting(s)

III. Consideration of and possible vote(s) on proposed or potential orders in cases on the daily signing agenda docket. The Commission may discuss and consider alterations, revisions, or
amendments to the proposed or potential orders. (Votes may be taken on individual cases, on the daily signing agenda docket as a whole, or both by individual cases and the remaining docket. The vote on daily signing agenda cases may be combined with the vote on 24-hour signing agenda cases.)

IV. Consideration of and possible vote(s) on proposed or potential orders in cases on attached 24-hour signing agenda docket.  The Commission may discuss and consider alterations, revisions, or amendments to the proposed or potential orders.  (Votes may be taken on individual cases on the 24-hour signing agenda docket as a whole, or both by individual cases and the remaining docket.)

V. Case No. OSF2024-000262, Application of Mark Argenbright, Administrator of the Oklahoma Universal Service Fund, Pursuant to OAC 165:59-3-13(a) & (b), to Consider or Adjust the Oklahoma Universal Service Fund Assessment and Establish a Repository for
Quarterly Status Reports (“Application”):

A. Discussion, possible hearing and possible vote(s) on Motion to Advance Hearing on the Merits to be Heard by the Commission En Banc filed by Mark Argenbright, Administrator of the Oklahoma Universal Service Fund and Director of the Public
Utility Division of the Commission

B. Discussion, possible public comment, possible hearing and possible vote(s) to adjust the Oklahoma Universal Service Fund assessment factor and grant any other necessary relief pursuant to the Application

C. Consideration of and possible vote(s) on proposed or potential order(s) regarding Item V. (A) and (B), including alterations, revisions, or amendments to such order(s) proposed at the meeting

VI. Presentation and discussion, including public comment, regarding the Draft 2026 Integrated Resource Plan of Oklahoma Gas and Electric Company

VII. Adjournment

*********

BEFORE THE CORPORATION COMMISSION OF THE STATE OF
OKLAHOMA DAILY SIGNING AGENDA (PROPOSED ORDERS)

Case Number CD2022-005095 Order Type Dismissal Order RSO OKC
Parties UPLAND OPERATING LLC (Applicant) Relief Type(s) Location Exception
1st Legal Loc./County S3 T20N R26W / Ellis
Order Title ORDER DISMISSING CAUSE

Case Number CD2023-000724 Order Type Dismissal Order RSO OKC
Parties UPLAND OPERATING LLC (Applicant) Relief Type(s) Location Exception
1st Legal Loc./County S7 T20N R25W / Ellis
Order Title ORDER DISMISSING CAUSE

Case Number CD2023-001308 Order Type Dismissal Order RSO OKC
Parties UPLAND OPERATING LLC (Applicant) Relief Type(s) Location Exception
1st Legal Loc./County S4 T20N R26W / Ellis
Order Title ORDER DISMISSING CAUSE

Case Number CD2023-002182 Order Type Dismissal Order RSO OKC
Parties BNK PETROLEUM (US) INC (Applicant) Relief Type(s) Location Exception
1st Legal Loc./County S9 T4S R4E / Johnston
Order Title FINAL ORDER DISMISSING CAUSE

Case Number CD2023-002183 Order Type Dismissal Order RSO OKC
Parties BNK PETROLEUM (US) INC (Applicant) Relief Type(s) Location Exception
1st Legal Loc./County S9 T4S R4E / Johnston
Order Title FINAL ORDER DISMISSING CASE

Case Number CD2023-002261 Order Type Dismissal Order RSO OKC
Parties UPLAND OPERATING LLC (Applicant) Relief Type(s) Location Exception
1st Legal Loc./County S8 T19N R24W / Ellis
Order Title ORDER DISMISSING CAUSE

Case Number CD2023-002980 Order Type Final RSO OKC
Parties BNK PETROLEUM (US) INC (Applicant) Relief Type(s) Location Exception
1st Legal Loc./County S12 T4S R3E / Carter
Order Title FINAL ORDER OF THE COMMISSION
HORIZONTAL WELL LOCATION
EXCEPTION

Case Number CD2025-001328 Order Type DMOA RSO OKC
Parties CANVAS ENERGY LLC (Applicant) Relief Type(s) Drilling and Spacing Unit
1st Legal Loc./County S22 T16N R6W / Kingfisher
Order Title ORDER DISMISSING CAUSE

Case Number CD2025-001329 Order Type DMOA RSO OKC
Parties CANVAS ENERGY LLC (Applicant) Relief Type(s) Location Exception
1st Legal Loc./County S22 T16N R6W / Kingfisher
Order Title ORDER DISMISSING CAUSE

Case Number CD2025-001908 Order Type DMOA RSO OKC
Parties CANVAS ENERGY LLC (Applicant) Relief Type(s) Pooling
1st Legal Loc./County S26 T23N R12W / Major
Order Title ORDER DISMISSING CAUSE

Case Number CD2025-001909 Order Type DMOA RSO OKC
Parties CANVAS ENERGY LLC (Applicant) Relief Type(s) Pooling
1st Legal Loc./County S35 T23N R12W / Major
Order Title ORDER DISMISSING CAUSE

Case Number CD2025-002103 Order Type Final RSO OKC
Parties VALIDUS ENERGY II MIDCON LLC
(Applicant)
Relief Type(s) Multi-unit horizontal well
1st Legal Loc./County S14 T10N R6W / Canadian
Order Title FINAL ORDER OF THE COMMISSION
MULTIUNIT HORIZONTAL WELL

Case Number CD2025-002105 Order Type Final RSO OKC
Parties VALIDUS ENERGY II MIDCON LLC
(Applicant)
Relief Type(s) Multi-unit horizontal well
1st Legal Loc./County S14 T10N R6W / Canadian
Order Title FINAL ORDER OF THE COMMISSION
MULTIUNIT HORIZONTAL WELL

Case Number CD2025-002116 Order Type Final RSO OKC
Parties VALIDUS ENERGY II MIDCON LLC
(Applicant)
Relief Type(s) Multi-unit horizontal well
1st Legal Loc./County S15 T10N R6W / Canadian
Order Title FINAL ORDER OF THE COMMISSION
MULTIUNIT HORIZONTAL WELL

Case Number CD2025-002204 Order Type DMOA RSO OKC
Parties OVINTIV USA INC (Applicant) Relief Type(s) Change of operator
1st Legal Loc./County S14 T14N R8W / Canadian
Order Title ORDER OF THE COMMISSION
DISMISSING CAUSE

Case Number CD2025-002349 Order Type Interim RSO OKC
Parties DEVON ENERGY PRODUCTION COMPANY
LP (Applicant)
Relief Type(s) Multi-unit horizontal well
1st Legal Loc./County S12 T14N R20W / Custer
Order Title INTERIM ORDER OF THE COMMISSION

Case Number CD2025-002350 Order Type Interim RSO OKC
Parties DEVON ENERGY PRODUCTION COMPANY
LP (Applicant)
Relief Type(s) Location Exception
1st Legal Loc./County S12 T14N R20W / Custer
Order Title INTERIM ORDER OF THE COMMISSION

Case Number CD2025-002351 Order Type Interim RSO OKC
Parties DEVON ENERGY PRODUCTION COMPANY
LP (Applicant)
Relief Type(s) Multi-unit horizontal well
1st Legal Loc./County S12 T14N R20W / Custer
Order Title INTERIM ORDER OF THE COMMISSION

Case Number CD2025-002352 Order Type Interim RSO OKC
Parties DEVON ENERGY PRODUCTION COMPANY
LP (Applicant)
Relief Type(s) Location Exception
1st Legal Loc./County S12 T14N R20W / Custer
Order Title INTERIM ORDER OF THE COMMISSION

Case Number CD2025-002353 Order Type Interim RSO OKC
Parties DEVON ENERGY PRODUCTION COMPANY
LP (Applicant)
Relief Type(s) Multi-unit horizontal well
1st Legal Loc./County S12 T14N R20W / Custer
Order Title INTERIM ORDER OF THE COMMISSION

Case Number CD2025-002354 Order Type Interim RSO OKC
Parties DEVON ENERGY PRODUCTION COMPANY
LP (Applicant)
Relief Type(s) Location Exception
1st Legal Loc./County S12 T14N R20W / Custer
Order Title INTERIM ORDER OF THE COMMISSION

Case Number CD2025-002542 Order Type Final RSO OKC
Parties VALIDUS ENERGY II MIDCON LLC
(Applicant)
Relief Type(s) Multi-unit horizontal well
1st Legal Loc./County S3 T9N R6W / Canadian
Order Title FINAL ORDER OF THE COMMISSION
MULTIUNIT HORIZONTAL WELL

Case Number CD2025-002880 Order Type Final RSO OKC
Parties CAMINO NATURAL RESOURCES LLC
(Applicant)
Relief Type(s) Location Exception
1st Legal Loc./County S24 T6N R7W / Grady
Order Title FINAL ORDER OF THE COMMISSION

Case Number CD2025-002929 Order Type DMOA RSO OKC
Parties CANVAS ENERGY LLC (Applicant) Relief Type(s) Rule – Waiver or Exception
1st Legal Loc./County S35 T23N R12W / Major
Order Title ORDER DISMISSING CAUSE

Case Number CD2025-004142 Order Type Final RSO TUL
Parties NADEL AND GUSSMAN LLC (Applicant) |
VOGEL EXPLORATION LLC (Applicant)
Relief Type(s) Rule – Waiver or Exception
1st Legal Loc./County S2 T13N R19W / Custer
Order Title FINAL ORDER OF THE COMMISSION
WAIVER OF CONSENT

Case Number CD2026-000135 Order Type Final RSO TUL
Parties SANGUINE GAS EXPLORATION LLC
(Applicant)
Relief Type(s) Pooling
1st Legal Loc./County S33 T13N R12W / Blaine
Order Title FINDINGS AND ORDER

Case Number CD2026-000248 Order Type Final RSO OKC
Parties CONTINENTAL RESOURCES INC (Applicant) Relief Type(s) Pooling
1st Legal Loc./County S27 T1N R4W / Stephens
Order Title ORDER OF THE COMMISSION

Case Number CD2026-000249 Order Type Final RSO OKC
Parties CONTINENTAL RESOURCES INC (Applicant) Relief Type(s) Pooling
1st Legal Loc./County S34 T1N R4W / Stephens
Order Title ORDER OF THE COMMISSION

Case Number CD2026-000322 Order Type Interim RSO OKC
Parties MEWBOURNE OIL COMPANY (Applicant) Relief Type(s) Multi-unit horizontal well
1st Legal Loc./County S5 T13N R21W / Roger Mills
Order Title INTERIM ORDER OF THE COMMISSION
MULTIUNIT HORIZONTAL WELL

Case Number CD2026-000323 Order Type Interim RSO OKC
Parties MEWBOURNE OIL COMPANY (Applicant) Relief Type(s) Location Exception
1st Legal Loc./County S5 T13N R21W / Roger Mills
Order Title INTERIM ORDER OF THE COMMISSION
HORIZONTAL WELL LOCATION
EXCEPTION AND EXCEPTION TO OAC
165:10-3-28 C 2 B

Case Number CD2026-000384 Order Type DMOA RSO OKC
Parties MIDCON ENERGY DEVELOPMENT LLC
(Applicant) | MIDCON ENERGY PDP LLC
(Applicant)
Relief Type(s) Prior Order/Permit –
Reinstate/Suspend/Terminate/Vacate
1st Legal Loc./County S35 T14N R8W / Canadian
Order Title ORDER DISMISSING CAUSE

Case Number CD2026-000426 Order Type Final RSO TUL
Parties CULBREATH OIL & GAS CO., INC.
(Applicant)
Relief Type(s) Pooling
1st Legal Loc./County S3 T10N R7E / Seminole
Order Title FINAL ORDER OF THE COMMISSION

Case Number CD2026-000427 Order Type Final RSO TUL
Parties CULBREATH OIL & GAS CO., INC.
(Applicant)
Relief Type(s) Pooling
1st Legal Loc./County S3 T10N R7E / Seminole
Order Title FINAL ORDER OF THE COMMISSION

Case Number CD2026-000428 Order Type Final RSO TUL
Parties CULBREATH OIL & GAS CO., INC.
(Applicant)
Relief Type(s) Pooling
1st Legal Loc./County S3 T10N R7E / Seminole
Order Title FINAL ORDER OF THE COMMISSION

Case Number CD2026-000622 Order Type DMOA RSO OKC
Parties MIDCON ENERGY DEVELOPMENT LLC
(Applicant) | MIDCON ENERGY PDP LLC
(Applicant)
Relief Type(s) Pooling
1st Legal Loc./County S35 T14N R8W / Canadian
Order Title ORDER DISMISSING CAUSE

Case Number CD2026-000727 Order Type Final RSO OKC
Parties MEWBOURNE OIL COMPANY (Applicant) Relief Type(s) Drilling and Spacing Unit
1st Legal Loc./County S11 T9N R11W / Caddo
Order Title REPORT OF THE COMMISSION

Case Number CD2026-000776 Order Type Interim RSO TUL
Parties VALIDUS ENERGY II MIDCON LLC
(Applicant)
Relief Type(s) Increased well density
1st Legal Loc./County S11 T13N R16W / Custer
Order Title INTERIM ORDER OF THE COMMISSION
INCREASED DENSITY

Case Number CD2026-001049 Order Type Final RSO OKC
Parties OXLEY ENERGY LLC (Applicant) Relief Type(s) Pooling
1st Legal Loc./County S11 T6N R17E / Latimer
Order Title ORDER OF THE COMMISSION

Case Number CD2026-001214 Order Type Motion RSO TUL
Parties ANTHEM ARAPAHO LLC (Applicant) Relief Type(s) Pooling
1st Legal Loc./County S1 T13N R18W / Custer
Order Title ORDER GRANTING MOTION TO SET
CASE FOR HEARING

Case Number CD2026-001243 Order Type Interim RSO OKC
Parties MEWBOURNE OIL COMPANY (Applicant) Relief Type(s) Increased well density
1st Legal Loc./County S11 T9N R10W / Caddo
Order Title INTERIM ORDER OF THE COMMISSION

BEFORE THE CORPORATION COMMISSION OF THE STATE OF
OKLAHOMA 24 HR SIGNING AGENDA (PROPOSED ORDERS)

Case Number PUD2025-000069 Order Type Final RSO OKC
Parties AEP OKLAHOMA TRANSMISSION
COMPANY INC (Applicant)
Relief In Caption IN THE MATTER OF THE APPLICATION OF
AEP OKLAHOMA TRANSMISSION COMPANY, INC. FOR A
CERTIFICATE OF AUTHORITY PERMITTING IT TO REBUILD
ELECTRIC TRANSMISSION FACILITIES LOCATED IN
CARTER, COMANCHE, AND STEPHENS COUNTIES
Order Title FINAL ORDER GRANTING CERTIFICATE
OF AUTHORITY

Case Number PUD2025-000084 Order Type Motion RSO OKC
Parties OKLAHOMA GAS AND ELECTRIC
COMPANY (Applicant)
Relief In Caption IN THE MATTER OF THE APPLICATION
OF OKLAHOMA GAS AND ELECTRIC COMPANY FOR
COMMISSION PREAPPROVAL OF NEW GENERATION
CAPACITY PURSUANT TO 17 O.S. § 286(C) AND RIDER
COST RECOVERY
Order Title ORDER GRANTING MOTION TO
ASSOCIATE COUNSEL

Case Number PUD2026-000001 Order Type Motion RSO OKC
Parties AEP OKLAHOMA TRANSMISSION
COMPANY INC (Applicant)
Relief In Caption IN THE MATTER OF THE APPLICATION
OF AEP OKLAHOMA TRANSMISSION COMPANY, INC. FOR
A CERTIFICATE OF AUTHORITY PERMITTING IT TO
REBUILD ELECTRIC TRANSMISSION FACILITIES LOCATED
IN STEPHENS COUNTY
Order Title ORDER GRANTING MOTION TO
DETERMINE NOTICE

Case Number PUD2026-000013 Order Type Motion RSO OKC
Parties ARGENBRIGHT, MARK (Applicant) |
GREENLIGHT GAS LLC (Respondent)
Relief In Caption APPLICATION OF MARK ARGENBRIGHT,
DIRECTOR OF THE PUBLIC UTILITY DIVISION, OKLAHOMA
CORPORATION COMMISSION, FOR A PUBLIC HEARING TO
REVIEW AND MONITOR APPLICATION OF THE FUEL
ADJUSTMENT CLAUSES OF GREENLIGHT GAS, LLC, WEST
TEXAS GAS UTILITY, LLC, AND FIRST NATURAL GAS FOR
THE CALENDAR YEAR 2025 AND FOR A PRUDENCE
REVIEW OF THE FUEL PROCUREMENT PROCESSES AND
COSTS OF GREENLIGHT GAS, LLC, WEST TEXAS GAS
UTILITY, LLC, AND FIRST NATURAL GAS FOR THE
CALENDAR YEAR 2025
Order Title ORDER GRANTING MOTION FOR
ORDER PRESCRIBING NOTICE

Case Number PUD2026-000013 Order Type Motion RSO OKC
Parties ARGENBRIGHT, MARK (Applicant) |
GREENLIGHT GAS LLC (Respondent)
Relief In Caption APPLICATION OF MARK ARGENBRIGHT,
DIRECTOR OF THE PUBLIC UTILITY DIVISION, OKLAHOMA
CORPORATION COMMISSION, FOR A PUBLIC HEARING TO
REVIEW AND MONITOR APPLICATION OF THE FUEL
ADJUSTMENT CLAUSES OF GREENLIGHT GAS, LLC, WEST
TEXAS GAS UTILITY, LLC, AND FIRST NATURAL GAS FOR
THE CALENDAR YEAR 2025 AND FOR A PRUDENCE
REVIEW OF THE FUEL PROCUREMENT PROCESSES AND
COSTS OF GREENLIGHT GAS, LLC, WEST TEXAS GAS
UTILITY, LLC, AND FIRST NATURAL GAS FOR THE
CALENDAR YEAR 2025
Order Title ORDER GRANTING MOTION TO
ESTABLISH PROCEDURAL SCHEDULE

Case Number PUD2026-000014 Order Type Motion RSO OKC
Parties ARGENBRIGHT, MARK (Applicant) |
ARKANSAS VALLEY ELECTRIC
COOPERATIVE (Respondent)
Relief In Caption APPLICATION OF MARK ARGENBRIGHT,
DIRECTOR OF THE PUBLIC UTILITY DIVISION, OKLAHOMA
CORPORATION COMMISSION, FOR A PUBLIC HEARING TO
REVIEW AND MONITOR APPLICATION OF THE
PURCHASED POWER ADJUSTMENT CLAUSE OF
ARKANSAS VALLEY ELECTRIC COOPERATIVE,
NORTHEAST OKLAHOMA ELECTRIC COOPERATIVE, RICH
MOUNTAIN ELECTRIC COOPERATIVE, AND SOUTHWEST
ARKANSAS ELECTRIC COOPERATIVE FOR THE
CALENDAR YEAR 2025 AND FOR A PRUDENCE REVIEW
OF THE PURCHASED POWER AND FUEL PROCUREMENT
PROCESSES AND COSTS OF ARKANSAS VALLEY
ELECTRIC COOPERATIVE, NORTHEAST OKLAHOMA
ELECTRIC COOPERATIVE, RICH MOUNTAIN ELECTRIC
COOPERATIVE, AND SOUTHWEST ARKANSAS ELECTRIC
COOPERATIVE FOR THE CALENDAR YEAR 2025
Order Title ORDER GRANTING MOTION FOR
ORDER PRESCRIBING NOTICE

Case Number PUD2026-000014 Order Type Motion RSO OKC
Parties ARGENBRIGHT, MARK (Applicant) |
ARKANSAS VALLEY ELECTRIC
COOPERATIVE (Respondent)
Relief In Caption APPLICATION OF MARK ARGENBRIGHT,
DIRECTOR OF THE PUBLIC UTILITY DIVISION, OKLAHOMA
CORPORATION COMMISSION, FOR A PUBLIC HEARING TO
REVIEW AND MONITOR APPLICATION OF THE
PURCHASED POWER ADJUSTMENT CLAUSE OF
ARKANSAS VALLEY ELECTRIC COOPERATIVE,
NORTHEAST OKLAHOMA ELECTRIC COOPERATIVE, RICH
MOUNTAIN ELECTRIC COOPERATIVE, AND SOUTHWEST
ARKANSAS ELECTRIC COOPERATIVE FOR THE
CALENDAR YEAR 2025 AND FOR A PRUDENCE REVIEW
OF THE PURCHASED POWER AND FUEL PROCUREMENT
PROCESSES AND COSTS OF ARKANSAS VALLEY
ELECTRIC COOPERATIVE, NORTHEAST OKLAHOMA
ELECTRIC COOPERATIVE, RICH MOUNTAIN ELECTRIC
COOPERATIVE, AND SOUTHWEST ARKANSAS ELECTRIC
COOPERATIVE FOR THE CALENDAR YEAR 2025
Order Title ORDER GRANTING MOTION TO
ESTABLISH PROCEDURAL SCHEDULE

Case Number PUD2026-000015 Order Type Final RSO OKC
Parties PUBLIC SERVICE COMPANY OF
OKLAHOMA (Applicant)
Relief In Caption IN THE MATTER OF THE APPLICATION
OF PUBLIC SERVICE COMPANY OF OKLAHOMA FOR
AUTHORITY PERMITTING IT TO ISSUE SENIOR
UNSECURED NOTES AND/OR UNSECURED PROMISSORY
NOTES IN A PRINCIPAL AMOUNT OF $3,250,000,000
Order Title FINAL ORDER GRANTING CERTIFICATE
OF AUTHORITY

Case Number PUD2026-000016 Order Type Final RSO OKC
Parties ARGENBRIGHT, MARK (Applicant) |
OKLAHOMA GAS AND ELECTRIC
COMPANY (Respondent)
Relief In Caption APPLICATION OF MARK ARGENBRIGHT,
DIRECTOR OF THE PUBLIC UTILITY DIVISION, OKLAHOMA
CORPORATION COMMISSION, FOR AN ORDER OF THE
COMMISSION TO RETAIN AND APPROVE COST
RECOVERY FOR AN INDEPENDENT EVALUATOR TO
MONITOR A REQUEST FOR PROPOSALS AND
COMPETITIVE BIDDING PROCESS OF OKLAHOMA GAS
AND ELECTRIC COMPANY SEEKING PROPOSALS FOR
NATURAL GAS STORAGE
Order Title FINAL ORDER

Case Number PUD2026-000018 Order Type Motion RSO OKC
Parties ARGENBRIGHT, MARK (Applicant) |
OKLAHOMA GAS AND ELECTRIC
COMPANY (Respondent)
Relief In Caption APPLICATION OF MARK ARGENBRIGHT,
DIRECTOR OF THE PUBLIC UTILITY DIVISION, OKLAHOMA
CORPORATION COMMISSION, FOR A PUBLIC HEARING TO
REVIEW AND MONITOR APPLICATION OF THE FUEL
ADJUSTMENT CLAUSE OF OKLAHOMA GAS AND
ELECTRIC COMPANY FOR THE CALENDAR YEAR 2025
AND FOR A PRUDENCE REVIEW OF THE FUEL
PROCUREMENT PROCESSES AND COSTS OF OKLAHOMA
GAS AND ELECTRIC COMPANY FOR THE CALENDAR
YEAR 2025
Order Title ORDER GRANTING MOTION FOR
ORDER PRESCRIBING NOTICE

Case Number PUD2026-000018 Order Type Motion RSO OKC
Parties ARGENBRIGHT, MARK (Applicant) |
OKLAHOMA GAS AND ELECTRIC
COMPANY (Respondent)
Relief In Caption APPLICATION OF MARK ARGENBRIGHT,
DIRECTOR OF THE PUBLIC UTILITY DIVISION, OKLAHOMA
CORPORATION COMMISSION, FOR A PUBLIC HEARING TO
REVIEW AND MONITOR APPLICATION OF THE FUEL
ADJUSTMENT CLAUSE OF OKLAHOMA GAS AND
ELECTRIC COMPANY FOR THE CALENDAR YEAR 2025
AND FOR A PRUDENCE REVIEW OF THE FUEL
PROCUREMENT PROCESSES AND COSTS OF OKLAHOMA
GAS AND ELECTRIC COMPANY FOR THE CALENDAR
YEAR 2025
Order Title ORDER GRANTING MOTION TO
ESTABLISH PROCEDURAL SCHEDULE