Deadline approaching for Magellan’s extended open season in Texas

Friday is the deadline of an extended supplemental open season on Magellan Midstream Partners, L.P.’s western leg of its pipeline system in Texas.

The Tulsa-based company recently announced the extension and said binding commitments for transportation volume would be due by 5 p.m. Central Time on Jan. 3, 2020. The extension gave interested shippers additional time to make commitments.

 

Magellan is in the process of expanding the capacity of its west Texas refined products pipeline system to approximately 175,000 barrels per day (bpd) from its current capacity of 100,000 bpd. In addition, the partnership is currently building a new refined products terminal in Midland, Texas.

Based on the timing of current construction activities, Magellan expects both the west Texas refined products pipeline expansion and new Midland terminal to be operational in mid-2020.

Magellan’s west Texas pipeline system primarily transports gasoline and diesel fuel to demand centers in Abilene, Midland/Odessa and El Paso, Texas as well as New Mexico. The pipeline system also can access markets in Arizona and Mexico via connections to third-party pipelines.

Subject to the results of the supplemental open season, Magellan is considering the addition of another 25,000 bpd of capacity on the west Texas pipeline, for a total capacity up to 200,000 bpd, which could be operational by the end of 2021.