Cyrogenic gas plant being relocated to Cashion

 

The relocation of a 60-million cubic feet a day cryogenic gas processing plant from Tonkawa to Cashion has resulted in a contract to Tulsa’s Ross Group.

The firm’s contract includes dismantling, relocation and re-erection of of the plant.

Ross Group has offices in Oklahoma City and they will provide the management of the project. Ross will also do the foundation design at the site near Cashion.

Work is laready underway.  Mike Smith, operating officer of Ross Group Design-Build indicated the project should be completed in the first quarter of 2019.